MIL-PRF-39016/29G
After installation of spreader mounting pad perform the following tests as specified in the qualification
inspection table of MIL-PRF-39016 in the order shown below:
Insulation resistance, dielectric withstanding voltage, static contact resistance; specified pickup
(latch/reset) value (voltage), hold, coil resistance, operate and release time, contact dynamic
characteristics, coil transient suppression (when specified), solderatiliby, seal, visual and mechanical
inspection (external).
Qualification inspection (reduced testing for previously qualified relays) for relays supplied with spreader
mounting pads (-061 through -072), two (2) units of the 26.5 volt rated coil voltage (-065) shall be tested as
specified below:
Before installation of spreader mounting pad, perform the following tests as specified in the qualification
inspection table of MIL-PRF-39016 in the order shown below:
For failure rate level L only. Screening.
(Failure rate level "L" is inactive for new design).
For failure rate levels M, P, and R: Vibration (sinusoidal) test duration shall be 10 minutes, vibration
(random), and screening.
After installation of spreader mounting pad perform the following tests as specified in the qualification
inspection table of MIL-PRF-39016 in the order shown below:
Insulation resistance, dielectric withstanding voltage, static contact resistance, specified pickup
(latch/reset) value (voltage), coil resistance, operate and release time, contact dynamic characteristics,
coil transient suppression (when specified), solderability, seal, visual and mechanical inspection
(external).
Group A testing for relays supplied with spreader mounting pads (-061 through -072), shall be tested as
specified below:
Perform seal test immediately, preceding the subgroup A2 electrical tests. Relay leads shall be formed and
the spreader mounting pad removed before the seal test. After the seal test, the spreader mounting pad
shall be rigidly attached to the relay and the remaining group A tests performed.
Qualification inspection (reduced testing) and sample size: See table III.
If the relays produced for MIL-PRF-39016/29 are similar in construction and design except for diodes
and coils, to the relays produced for MIL-PRF-39016/30, then reduced testing for qualification of MIL-
PRF-39016/29 relays may be performed concurrent with or subsequent to successful qualification of
MIL-PRF-39016/30 relays. For reduced testing see table III.
TABLE III. Qualification inspection (reduced testing).
Examination or test
2 units each coil voltage Q1 of qualification
inspection table
1 unsealed sample unit for internal examination.
SUPERSESSION DATA:
Supersession data: See table IV.