TABLE II. First article inspection.
Inspection |
Requirement paragraph |
Method paragraph |
Number of sample units to be inspected |
Number of failures allowed |
Group I Visual and mechanical inspection Electrical characteristics Insulation resistance Dielectric withstanding voltage (at sea level) Group II Mounting stud and terminal strength Static spring return force - (when specified) Thermal shock Solderability Vibration Shock Acceleration (when specified) Moisture resistance Life Group III Static spring return force (when specified) Magnetic effect (when specified) Altitude (when specified) High temperature Low temperature Salt spray Sand and dust (when specified) Explosion (when specified) Coil life |
3.1, 3.4, 3.5, 3.8, and 3.9 3.5.1 3.5.2 3.5.3 3.5.4 3.5.5 3.6.1 3.6.2 3.6.3 3.6.4 3.6.5 3.6.6 3.7 3.5.5 3.5.6 3.6.7 3.6.8 3.6.9 3.6.10 3.6.11 3.6.12 3.7.1 |
4.7.1 4.7.2 4.7.3 4.7.4.1 4.7.5 4.7.6 4.7.8 4.7.9 4.7.10 4.7.11 4.7.12 4.7.13 4.7.20 4.7.6 4.7.7 4.7.14 4.7.15 4.7.16 4.7.17 4.7.18 4.7.19 4.7.21 |
12 6 6 |
0 0 0 |
4.5.3 Failures. One or more failures shall be cause for refusal to grant first article approval.
4.6 Conformance inspection.
4.6.1 Inspection lot. An inspection lot shall consist of one week's production of solenoids of the same design, materials, and production processes, produced under essentially the same conditions and offered for inspection at one time. Where production is less than 200 solenoids per week, a lot shall consist of two consecutive weeks production. The date code shall indicate that the solenoids were produced during the first week.
4.6.2 Group A inspection. The group A inspection shall consist of the inspection specified in table III, in the order shown.